Time - Cost Relationships for Superstructure Projects in Turkey
| dc.contributor.author | Dikmen, Seyyit Ümit | |
| dc.contributor.author | Akbıyıklı, Rıfat | |
| dc.contributor.author | Sönmez, Murat | |
| dc.date.accessioned | 2019-08-27T13:26:53Z | |
| dc.date.available | 2019-08-27T13:26:53Z | |
| dc.date.issued | 2020 | |
| dc.description.abstract | The concept of time-cost relationship in construction projects was first introduced by Bromilow. Bromilow used the data of the superstructure projects completed in Australia in the creation of the proposed time-cost model (BTC model). The aim of this study is to determine the time-cost relationship of superstructure projects in Turkey. Time and cost data of superstructure projects completed between the years of 1999-2018 was used in the study. Data was grouped primarily on the basis of the intended use of buildings (individual buildings, educational buildings, hospitals, industrial buildings and social housing), and then time-cost relationships were separately determined for each group. In addition, the effects of the parameters such as exchange rates and the number of non-working days on the time-cost relationship were investigated statistically. | |
| dc.identifier.citation | Sönmez, M., Dikmen, S. Ü. ve Akbıyıklı, R. (2020).Time - cost relationships for superstructure projects in Turkey. Teknik Dergisi. 32(2), pp.1-28. | |
| dc.identifier.doi | 10.18400/TEKDERG.456761 | |
| dc.identifier.issn | 1300-3453 | |
| dc.identifier.scopus | 2-s2.0-85086437070 | |
| dc.identifier.uri | https://doi.org/10.18400/tekderg.456761 | |
| dc.identifier.uri | https://hdl.handle.net/20.500.11779/1130 | |
| dc.language.iso | en | |
| dc.publisher | TMMOB İnşaat Mühendisleri Odası | |
| dc.relation.ispartof | Teknik Dergi | |
| dc.rights | info:eu-repo/semantics/openAccess | |
| dc.subject | Superstructure projects | |
| dc.subject | Bromilow’s btc model | |
| dc.subject | Time-cost relationship | |
| dc.subject | Construction management | |
| dc.title | Time - Cost Relationships for Superstructure Projects in Turkey | |
| dc.type | Article | |
| dspace.entity.type | Publication | |
| gdc.author.id | Seyyit Ümit Dikmen / 0000-0002-4003-1368 | |
| gdc.author.institutional | Dikmen, Seyyit Ümit | |
| gdc.bip.impulseclass | C5 | |
| gdc.bip.influenceclass | C5 | |
| gdc.bip.popularityclass | C4 | |
| gdc.coar.access | open access | |
| gdc.coar.type | text::journal::journal article | |
| gdc.description.department | Mühendislik Fakültesi, İnşaat Mühendisliği Bölümü | |
| gdc.description.endpage | 28 | |
| gdc.description.issue | 2 | |
| gdc.description.publicationcategory | Makale - Uluslararası Hakemli Dergi - Kurum Öğretim Elemanı | |
| gdc.description.scopusquality | N/A | |
| gdc.description.startpage | 1 | |
| gdc.description.volume | 31 | |
| gdc.description.woscitationindex | Science Citation Index Expanded | |
| gdc.description.wosquality | Q4 | |
| gdc.identifier.openalex | W2971323118 | |
| gdc.identifier.trdizinid | 403545 | |
| gdc.identifier.wos | WOS:000518474000004 | |
| gdc.index.type | WoS | |
| gdc.index.type | Scopus | |
| gdc.index.type | TR-Dizin | |
| gdc.oaire.accesstype | GOLD | |
| gdc.oaire.diamondjournal | false | |
| gdc.oaire.impulse | 3.0 | |
| gdc.oaire.influence | 2.6876867E-9 | |
| gdc.oaire.isgreen | true | |
| gdc.oaire.keywords | construction management | |
| gdc.oaire.keywords | Bromilow’s time-cost (BTC) model;building projects;construction management;duration estimation;regression analysis | |
| gdc.oaire.keywords | [No Keywords] | |
| gdc.oaire.keywords | building projects | |
| gdc.oaire.keywords | Time-cost relationship | |
| gdc.oaire.keywords | Time-cost relationship;Bromilow’s BTC model;superstructure projects;construction management | |
| gdc.oaire.keywords | İnşaat Mühendisliği | |
| gdc.oaire.keywords | Civil Engineering | |
| gdc.oaire.keywords | regression analysis | |
| gdc.oaire.keywords | duration estimation | |
| gdc.oaire.keywords | Bromilow's time-cost (BTC) model | |
| gdc.oaire.keywords | Construction management | |
| gdc.oaire.keywords | Bromilow’s BTC model | |
| gdc.oaire.keywords | Superstructure projects | |
| gdc.oaire.popularity | 4.4786606E-9 | |
| gdc.oaire.publicfunded | false | |
| gdc.oaire.sciencefields | 05 social sciences | |
| gdc.oaire.sciencefields | 0211 other engineering and technologies | |
| gdc.oaire.sciencefields | 02 engineering and technology | |
| gdc.oaire.sciencefields | 0502 economics and business | |
| gdc.openalex.collaboration | National | |
| gdc.openalex.fwci | 0.62879099 | |
| gdc.openalex.normalizedpercentile | 0.73 | |
| gdc.opencitations.count | 2 | |
| gdc.plumx.crossrefcites | 2 | |
| gdc.plumx.mendeley | 14 | |
| gdc.plumx.scopuscites | 5 | |
| gdc.publishedmonth | Mart | |
| gdc.scopus.citedcount | 5 | |
| gdc.virtual.author | Dikmen, Seyit Ümit | |
| gdc.virtual.author | Akbıyıklı, Rıfat | |
| gdc.wos.citedcount | 4 | |
| gdc.wos.collaboration | Uluslararası işbirliği ile yapılmayan - HAYIR | |
| gdc.wos.documenttype | Article | |
| gdc.wos.indexdate | 2020 | |
| gdc.wos.publishedmonth | Mart | |
| gdc.yokperiod | YÖK - 2019-20 | |
| relation.isAuthorOfPublication | 09f16a34-c2d2-4c0f-a2a1-be8e7842a65a | |
| relation.isAuthorOfPublication | 4e0d489a-ac3b-432b-bb0f-3467d424a771 | |
| relation.isAuthorOfPublication.latestForDiscovery | 09f16a34-c2d2-4c0f-a2a1-be8e7842a65a | |
| relation.isOrgUnitOfPublication | c90327d7-cf5a-4775-a458-1dbb7ea10e32 | |
| relation.isOrgUnitOfPublication | 0d54cd31-4133-46d5-b5cc-280b2c077ac3 | |
| relation.isOrgUnitOfPublication | a6e60d5c-b0c7-474a-b49b-284dc710c078 | |
| relation.isOrgUnitOfPublication.latestForDiscovery | c90327d7-cf5a-4775-a458-1dbb7ea10e32 |
Files
Original bundle
1 - 1 of 1
Loading...
- Name:
- 10.18400-tekderg.456761-680064.pdf
- Size:
- 1.51 MB
- Format:
- Adobe Portable Document Format
- Description:
- Yayıncı Sürümü - Makale
License bundle
1 - 1 of 1
No Thumbnail Available
- Name:
- license.txt
- Size:
- 1.44 KB
- Format:
- Item-specific license agreed upon to submission
- Description: